We have the best prices - equipment in stock, 1 year warranty
|
Equipment |
Production |
Price |
|
Two screw press with a dispenser and a cutoff mechanism |
1-1,5 tons/hour |
contract price |
| Two screw press with a dispenser and a cutoff mechanism | 2-3 tons/hour | contract price |
| Two screw press with a dispenser and a cutoff mechanism | 3-4 tons/hour | contract price |
| Two screw press with a dispenser and a cutoff mechanism | 5-6 tons/hour | contract price |
|
Rolling machine with |
2-10 tons/hour |
contract price |
|
Impact mechanical machine |
1 tone/hour |
contract price |
|
Fractional vibro disperser |
10 tones/hour |
contract price |
|
Mixer of forced |
2 tones and more |
contract price |
|
Hammer crusher |
2 tones and more |
contract price |
|
Rotary crusher (фрак. 25-100) |
30 tones and more |
contract price |
|
Crushing and sorting complex |
30 tones and more |
contract price |
|
Conveyor for cooling 22 кВт |
2-5 tones/hour |
contract price |
|
Conveyor with tape |
1m |
contract price |
|
Line for briquetting |
2 tones/hour |
contract price |
WE OFFER PREFABRICATED LINE FOR BRIQUETTING OF COAL OR PEAT, WITHOUT BINDERS.
1. 1. Line for briquetting of 8 tons per shift (8 working hours). The following set:
|
Component parts |
Production, tons/hour |
Quantity |
Energy consumption kWt/h |
|
Mixer of forced |
2 |
1 |
3,0 |
|
Extruding machine |
1 |
1 |
15,0 |
|
Conveyor thermal dryer |
2 |
1 |
15,0 |
|
Conveyor for cooling |
2 |
3 |
1,0 |
|
Totaly |
1 |
6 |
34,0 |
2. Line for briquetting of 16 tons per shift (8 working hours). The following set:
|
Component parts |
Production, tons/hour |
Quantity |
Energy consumption kWt/h |
|
Mixer of forced |
2 |
1 |
3,0 |
|
Extruding machine |
2 |
1 |
25,0 |
|
Conveyor thermal dryer |
2 |
1 |
15,0 |
|
Conveyor for cooling |
5 |
3 |
1,0 |
|
Totaly |
2 |
6 |
44,0 |
3. Line for briquetting of 35 tons per shift (8 working hours). The following set:
|
Component parts |
Production, tons/hour |
Quantity |
Energy consumption kWt/h |
|
Mixer of forced |
2 |
2 |
3,0 |
|
Extruding machine |
2 |
2 |
25,0 |
|
Conveyor thermal dryer |
4 |
1 |
30,0 |
|
Conveyor for cooling |
5 |
3 |
1,5 |
|
Totaly |
4 |
8 |
88,0 |
4. Line for briquetting of 50 tons per shift (8 working hours). The following set:
|
Component parts |
Production, tons/hour |
Quantity |
Energy consumption kWt/h |
|
Mixer of forced |
3 |
2 |
3,0 |
|
Extruding machine |
3 |
2 |
30,0 |
|
Conveyor thermal dryer |
6 |
1 |
30,0 |
|
Conveyor for cooling |
6 |
3 |
1,5 |
|
Totaly |
6 |
8 |
98,0 |
5. Line for briquetting of 100 tons per shift (8 working hours). The following set:
|
Component parts |
Production, tons/hour |
Quantity |
Energy consumption kWt/h |
|
Mixer of forced |
3 |
4 |
3,0 |
|
Extruding machine |
3 |
4 |
30,0 |
|
Conveyor thermal dryer |
12 |
2 |
30,0 |
|
Conveyor for cooling |
12 |
6 |
3,0 |
|
Totaly |
12 |
16 |
195,0 |
6. Line for briquetting of 160 tons per shift (8 working hours). The following set:
|
Component parts |
Production, tons/hour |
Quantity |
Energy consumption kWt/h |
|
Mixer of forced |
5 |
4 |
5,0 |
|
Extruding machine |
5 |
4 |
40,0 |
|
Conveyor thermal dryer |
20 |
4 |
15,0 |
|
Conveyor for cooling |
12 |
8 |
3,0 |
|
Totaly |
20 |
20 |
285,0 |
POSSIBLE SALE OF EQUIPMENT WITH THE TERRITORY OF RUSSIA IN RUBLES